www.mpcsite.com



Morris Power Construction - MPC
P.O. Box 23
630 Race Ave
Boswell, OK 74727

Site Map
duct-assembly_5.jpg
cowboy8.gif

Most Visited Pages


About Us
Welcome to the Website of Morris Power Construction.
We provide construction for various types of commercial power projects, with primary focus on renewable energy with wind turbine technology. In additon to wind farm construction projects, we do smaller wind turbine construction for residental, farms, educational centers, small businesses as well as both large and small corporations, and office park developments.





Clearwater 230 KVa Duct Bank


Progress Energy Duct Bank - St. Petersburg, FL

Clearwater, Florida was a sub-contract project. Progress Energy awarded the $42 million duct bank project to Kiewit Southern Co., a subsidiary of Kiewit Corporation. This project included procuring and installing four miles of a 16-duct utility in the corridor from the Bartow power plant to its northeast substation. The duct bank includes sixteen 8-inch-diameter PVC ducts, installed in an existing 100-foot-wide right-of-way, paralleling two existing high-voltage lines and a hot-oil line. The duct bank, which will carry a high-voltage power line, is encased in concrete.

Trench boxes were used during the duct bank construction to prevent the earth from caving into the 9-foot deep trench and to act as a forming system for the 6.5-foot-tall duct bank construction. Sixty pre-cast manholes 7 feet deep and 14 feet long were installed in sheeted excavations every 2,000 feet for cable pulling and splicing.

The part of this project that TJ Morris was involved with, entailed placing two 42-inch steel casings, each of 1,570 feet, and placing bundled eight 8-inch high-density polyethylene conduits under a major intersection. The pipe casing was pulled through a predrilled hole that utilized a directional drill process. Six additional bores were performed utilizing micro-tunneling and conventional jack and bore technology. These procedures allowed the duct bank to be constructed without demolishing the intersection and roadways, or interrupting traffic and to minimize the environmental impact. Grouting was done in a non-stop process, pumping grout inside the 2, 42-inch casings to keep the 345 KV transmission cables cool.

Morris Power Construction has experience in duct bank construction, thermal backfill and grouting for underground power transmission lines. Knowledge and experience go hand in hand. You can't have one without the other. In building a wind farm, the buried power cables create heat as voltage is passed through the cables. As wind speed increases, the amount of current passing through the buried cable increases as well. As the flow of current increases the buried cables can become very hot and, in some instances, the heat will melt the protective insulation causing a short circuit and literally burn up the cable.

Dirt surrounding the buried cables does not have thermal properties to dissipate this heat. This problem can be eliminated by placing thermal backfill in the trench, on top of the buried cable. The thermal backfill sets up quickly with little or no delay in backfilling the trench. The thermal backfill remains cool and will absorb the heat. As heat rises with the increase of wind speed, the thermal backfill will quickly dissipate the heat, avoiding a cable burnout. If you are building a wind farm, you should do it once and do it right. Every effort should be made to protect the investment by using thermal backfill over the buried cables.

Thermal grout is used inside of casings, when cables are routed through a casing such as under a road or a highway. The use of thermal grout, as with thermal backfill is for keeping the cables cool by dissapating heat. Thermal grout and thermal backfill should be mandatory for all buried power cables on all wind farms. If you are building a wind farm, you should do it once and do it right, include thermal backfill and thermal grout as insurance to prevent cable burnout. Morris Power Construction is very knowledgeable and well experienced in working with both thermal backfill and thermal grout.




42 inch casing




1570 feet




wind turbine duct assembly




wind turbine construction duct assembly




wind turbine duct bank wash




wind turbine construction duct assembly




wind turbine dual duct banks




duct integrity test wind turbine




wind turbine casing robot




wind turbine grouting




wind turbine Manholes




wind turbine power cable trailer














To register your website with Search Engines, use the listings below.



BuildTraffic.com search engine submission



Search Engine space Search Engine Submission and Internet Marketing Add Google Search engine @Submit!-FREE Search Engine Promotion Search engine spacer for USWEBSITES.COM Free Search Engine META Tag Help Analyzer Search engine spacer for Scrub The Web



Aeiwi




Search Engine Optimization and Free Submission




SortSite Top 10%
Website Quality Tests: Check Broken Links
SEO Analysis
Browser Compatibility
Check Accessibility
Check Web Standards